Chandler Regional Medical Center - Tower D

Chandler, AZ

Project Overview

Buesing serviced McCarthy on several scopes working on the Tower D project. This project included demolition and haul off, excavation and grading, and massive installation of a temporary Shoring System. We took what was once utilized as a parking lot and laid the groundwork for a successful new addition to be added to the Chandler Medical Center.

The Buesing Advantage on this project was our ability to provide a design-build solution for the temporary shoring and self perform all aspects of our work.

Location

Chandler, AZ

Owner

Dignity Health

General Contractor

McCarthy Building Companies

Project Duration

2018 - 2019

Services

  • Earth Retention Shoring
  • Site Work

Deliverables

  • 25,000 SF of Temporary Shoring
  • 54,000 CY Mass excavation and export from the site